B.1 Life-cycle stages and activities for coal seam gas operations
Table 18 Unique activities (for coal seam gas operations) during exploration and appraisal life-cycle stage for the Gloucester subregion
Activity |
---|
Abandonment |
Construction of access roads and easements (e.g. for drilling rigs and equipment) |
Drill cutting disposal |
Drill stem testing (extraction) |
Drilling and coring |
Fuel and oil |
Ground-based geophysics |
Materials delivery and storage |
Power and communications |
Pump testing |
Site clean-up and rehabilitation |
Site preparation |
Slug testing (injection) |
Surface core testing |
Surface water and mud storage and evaporation |
Temporary Accommodation, administration, workshop, depots, service facilities |
Table 19 Unique activities (for coal seam gas operations) during construction life-cycle stage for the Gloucester subregion
Activity |
---|
Accommodation, administration, workshop, depots, service facilities |
Brine storage ponds, pumps and water disposal pipelines |
Cementing and casing |
Construction of access roads and easements (e.g. for drilling rigs and equipment) |
Drill cutting disposal |
Drill stem testing (extraction) |
Drilling and logging |
Fuel and oil |
Fuel and oil storage facilities |
Gas-gathering pipeline networks |
Gas and water-gathering pipeline networks (well to processing plant) |
Gas compression stations |
Gas processing plant |
Groundwater monitoring bore construction |
Groundwater supply bore |
Hydraulic fracturing |
Hydraulic fracturing concentrate delivery |
Hydraulic fracturing fluid injection and disposal |
Hypersaline brine ponds |
Materials delivery and storage |
Perforation |
Power and communications |
Power generation facility (for processing plant) |
Remediation |
Sewage treatment and disposal |
Site preparation |
Surface water and mud storage and evaporation |
Treated water pond |
Trunk gas pipelines and associated easements (processing plant to town) |
Water treatment plant (RO, fixed resin, fixed disc, electrochemical, etc) |
Table 20 Unique activities (for coal seam gas operations) during production life-cycle stage for the Gloucester subregion
Activity |
---|
Accommodation, administration, workshop, depots, service facilities |
Brine storage ponds, pumps and water disposal pipelines |
Fuel and oil |
Fuel and oil storage facilities |
Gas-gathering pipeline networks |
Gas and water-gathering pipeline networks (well to processing plant) |
Gas compression stations |
Gas processing plant |
Groundwater monitoring bore construction or expansion |
Groundwater supply bore |
Hypersaline brine ponds |
Materials delivery and storage |
Operation access roads and easements (e.g. for drilling rigs and equipment) |
Power and communications |
Power generation facility (for processing plant) |
Sewage treatment and disposal |
Staff movement and activities |
Treated co-produced water disposal |
Treated water pond |
Trunk gas pipelines and associated easements (processing plant to town) |
Untreated co-produced water storage, processing and disposal (pilot stage only) |
Water and gas extraction |
Water treatment plant (RO, fixed resin, fixed disc, electrochemical, etc) |
Table 21 Unique activities (for coal seam gas operations) during decommissioning life-cycle stage for the Gloucester subregion
Activity |
---|
Fuel and oil |
Materials delivery and storage |
Pressure concrete completion |
Pressure concrete durability |
Process production plant |
Sewage treatment and disposal |
Table 22 Unique activities (for coal seam gas operations) during work-over life-cycle stage for the Gloucester subregion
Activity |
---|
Materials delivery and storage |
Site preparation |
Waste disposal |
Water sourcing (for injection) |
B.2 Life-cycle stages and activities for open-cut coal mines
Table 23 Unique activities (for open-cut coal mines) during exploration and appraisal life-cycle stage for the Gloucester subregion
Activity |
---|
Abandonment |
Drill cutting disposal |
Drilling and coring |
Ground-based geophysics |
Materials delivery and storage |
Site clean-up and rehabilitation |
Site preparation and construction for drilling activities |
Slug testing (injection) |
Surface core testing |
Surface water and mud storage and evaporation |
Temporary accommodation, administration, workshop, depots, stock piles, service facilities |
Table 24 Unique activities (for open-cut coal mines) during development life-cycle stage for the Gloucester subregion
Activity |
---|
Administration, workshop, service facilities (construction phase) |
Creek diversions, levee bunds, creek crossings |
Creek line diversion |
Dam construction |
Dam construction for freshwater storage |
Dam construction for mine water storage |
Dam construction for tailings storage |
Groundwater monitoring bore construction |
Groundwater supply bore |
Haul road construction |
Mine dewatering, treatment, reuse and disposal |
Off-lease and on-lease roadways (construction phase) |
Power, water and communications network: connection to existing grids |
Rail easement construction |
Rainwater and runoff diversion |
Temporary diesel generators (construction phase) |
Topsoil and waste rock dump site preparation |
Waste byproduct: treatment of water |
Waste rock blasting, excavation and storage |
Table 25 Unique activities (for open-cut coal mines) during production life-cycle stage for the Gloucester subregion
Activity |
---|
Coal excavation |
Coal on-site processing |
Coal on-site transport |
Coal on-site transport: stockpiles |
Coal processing waste material: handling, transport, storage |
Daily operational use of roads: haulage, inspection, maintenance, etc. |
Groundwater monitoring bore construction or expansion |
Haul road construction |
Materials storage facilities (e.g. fuel, oil and explosives) |
Mine dewatering, treatment, reuse and disposal |
New haul road construction |
Off-lease and on-lease roadways |
Onsite mine equipment storage |
Pit backfill (in-pit dump) |
Pit wall (stabilisation) dewatering, treatment, reuse and disposal |
Product coal stockpiling |
Run-of-mine (ROM) plants |
Tailings decant water dam |
Topsoil excavation and storage |
Waste rock blasting, excavation and storage |
Table 26 Unique activities (for open-cut coal mines) during closure life-cycle stage for the Gloucester subregion
Activity |
---|
Dismantling and removal of built infrastructure |
Pit backfill |
Post-closure mine site decontamination |
Post-closure water filling the pit |
Water management structures (dams, levee bunds and diversions) |
Table 27 Unique activities (for open-cut coal mines) during rehabilitation life-cycle stage for the Gloucester subregion
Activity |
---|
Groundwater monitoring bore: mine closure |
Recontoured landforms (slopes, gradients, etc.) |
Recontoured landforms (slopes, gradients, etc.): from building, rail and road infrastructure |
Revegetation |
METHODOLOGY FINALISATION DATE
- 1 Background and context
- 2 Methods
- 3 Case study: Gloucester subregion
- 4 Discussion
- Appendix A Effects, stressors and impact causes for the Gloucester subregion
- Appendix B Activities for the Gloucester subregion
- References
- Glossary
- Citation
- Acknowledgements
- Contributors to the Technical Programme
- About this submethodology